Regavim bridge
Client: Hasharon Diggers on behalf of the Trans-Israel Highway
Project description:
The project involved building six bridges for traffic while preserving the Mekorot water supply system, foundation work using deep foundation pylons, and casting a 1.5 m thick ceiling. Work on the project was halted when ancient graves were discovered onsite, but resumed after about two and half years after finding the requisite engineering solution.
Cost: NIS 54 million; Linom’s part: NIS 20.82 million
Date of completion: September 2009