Anabe tunnel
Client: Israel Railways Company Ltd.
Project description:
The project involved support-assisted preliminary excavation of an umbrella of pipes; concrete spraying; waterproofing and sealing; and casting two train tunnels on the segment connecting Ben-Gurion Airport to the city of Modi’in. The project was carried out at three excavation loci simultaneously, on a very tight deadline (one year). The project also included retaining walls with reinforcing deep foundation pylons and anchors.
Cost: NIS 72 million
Date of completion: September 2006